Tom Riley, Chair called the December 20, 2007 NAC meeting to order with Phil LaMoreaux, Everett Kittredge, Kevin McKenna, Eileen Kelly present. Also Andrew Pinard Selectmen, Jim Pickman and Jon Marden, NAC Review Committee and Cheryl Behr, Administrator.
Review and consideration of the December 17, 2007 Minutes:
The minutes were accepted as presented.
NEW BUSINESS
Review of Road Responses from bidders:
Phil LaMoreaux, Chair had done a spread sheet with information from the bidders. This information was discussed at length. Jon Marden also did a comparative breakdown of all the bidders for different categories.
Motion was made by Phil LaMoreaux to take the three lowest Road bidders, which are Hiltz, NEM and SCI and notify the contractors as final bidders for the Road. Motion seconded by Kevin McKenna. Motion carried 5-0.
Dates of Final Interviews Schedules:
Motion was made by Everett Kittredge to set the following dates for Interviews for the Highway Garage, and Police Station bidders.
December 28, 2007 Kinsman, Hooksett
January 3, 2008 Horn Construction, Rochester
January 4, 2008 CMGC, Bedford
Motion seconded by Kevin McKenna. Motion carried 5-0.
The consensus of the board was to allow 45 minutes for presentation and 15 minutes for questions for each building contractor per night.
Final selection date has not been decided upon at this time.
The final dollar amount will be needed for presentation to the Budget Committee for January 8, 2008.
Well Proposals
Everett Kittredge had prepared a spreadsheet for the Well proposals with the different components. Everett Kittredge suggested that a price of $350.00 needs to be added to any bidder who did not include the price for water testing. After considerable conversation, Jim Pickman suggested that a $10,000.00 dollar amount should be used to cover the total cost. The bids presented are good through March 31, 2008.
Jim Pickman, NAC Subcommittee Chair advised that a Generator, Toilet for the holding cell in the Police Station and Bullet Proof glass needs to be included as additional required material costs.
Phil LaMoreaux advised a Geotechnical report will also need to be considered and is the responsibility of the town which would provide bearing capacity where the buildings will be built (below the site work). Also, the town will be responsible for power to the site as well as all state and local permits.
Motion was made by Eileen Kelly for the NAC Steering Committee to meet on January 10, 2008. Motion seconded by Everett Kittredge. Motion carried 5-0.
An Independent Inspection Authority to check as work progresses was discussed.
Meeting Adjourned 8:35pm