Town of Bradford
Selectmen’s Meeting
February 16, 2010
5:00pm
Present: Charles Meany, Chair, Cheryl Behr, Administrator, Marge Cilley, Secretary and Mike Croteau, SEA
The purpose of this meeting is to open the bids on the West Road Bridge Project, with no other business being scheduled.
Mike Croteau, SEA thanked everyone for coming for the Bid opening for Bridge Replacement Safety work on West Road Bridge over Hoyt Brook. The opening of the bids was done in the order in which the bids were received as follows.
1. Morrill Construction, Inc. 373,555.50
2. T. Buck Construction 533,164.00
3. Neil H. Daniels, Inc. 399,734.00
4. Cold River Bridges 496,229.00
5. B U R Construction LLC 396,749.50
6. Hansen Construction 391,803.00
7. R M Piper 422,669.00
8. N E Earth Mechanics 429,418.00
Mike Croteau, SEA advised the low bidder as Morrill Construction, Inc, North Haverhill, NH at Three Hundred Seventy three Thousand Five Hundred Fifty Five Dollars and fifty cents ($373,555.50).
Question was asked as to when this will be started and the reply was late spring, late May or early June as the Wetland Permit wants the brook to be low flow. Construction duration is about five months.
Respectfully submitted
Marjorie R. Cilley